With that said, that's take a look at the Gold Line Extension in LA that is about 80% complete and on target for completion next year. The Gold Line Extension will connect Little Tokyo and East LA with Union Station in LA. The Six Mile long extension has a budget of $898 million with eight new stations, two of which will be underground. Groundbreaking took place in 2004 with completion slated for Mid-Summer of 2009. Check out some pictures below. You can learn more about the Gold Line at LA MetroRail's site.




1 comment:
Hey Pitch. Sorry I haven't added you to the CTA yet. Newsgator locked it up on me so i'm waiting to get it released. As soon as it does you're on.
Post a Comment